A month-by-month timeline for a coast where the roads are narrow, the good dates go early and the paperwork takes longer than anyone expects.
People ask me this in the first two minutes of almost every call, so let me answer it plainly: eighteen months is comfortable, twelve months is normal, and eight months is possible if you are flexible about the date. Under six months it can still be done, but the shape of the wedding starts to be decided by what is free rather than what you want.
The reason is not fashion. It is geography. There are perhaps thirty venues on this coast that can seat a hundred people well, one road connecting them, and a summer season that squeezes everything into twenty weekends. Booking early is not about being organised. It is about having a choice.
Eighteen to twelve months out
This is when the two decisions that shape everything else get made: the date and the venue. Everything after that is detail.
- Pick a fortnight, not a day. Venues will offer you a Friday you had not considered and it is often the better date.
- Come and see three or four places in one trip. Photographs flatten the difference between a terrace at sea level and one three hundred metres up.
- Decide roughly how many people. Sixty and a hundred are different weddings on this coast, not the same wedding with more chairs.
- Book the photographer. Good ones here take one wedding a weekend and they book further ahead than venues.
The couples who enjoy their engagement are the ones who made the two big decisions early and then stopped making decisions for a while.
Twelve to eight months out
Now the day starts to have a texture. This is when I book the people, not the things: celebrant, catering, music, flowers, hair and make-up. On the Amalfi Coast the supplier list is short and largely the same people I have worked with for twenty years, which is why this stage moves quickly if you let it.
It is also the moment to start the legal paperwork if you are marrying legally in Italy. Foreign couples routinely underestimate this. The documents themselves are not difficult, but they pass through a consulate and a comune, both of which move at their own pace and neither of which will be rushed in August.

Eight to four months out
Design, menus, and the parts of logistics your guests will feel: where they sleep, how they get from the airport, how they get from the ceremony to dinner when the road is closed for a procession. I walk the route myself at the same hour of day the wedding will happen, because Ravello at 5pm in July is a different town from Ravello at 5pm in April.
- Confirm the guest list properly and send invitations.
- Block hotel rooms in two price bands, not one.
- Fix transfers by land and sea — this is where most weddings here quietly go wrong.
- Taste the menu in the season you will eat it.
The last eight weeks
Very little should be undecided by now. What happens in these weeks is confirmation, seating, timings to the quarter hour, and the rehearsal. If I am doing my job, the last month is the calmest month of your engagement.
And if you have less time than this
Short timelines are not a disaster; they are a trade. You give up some choice over venue and date and you keep everything else. I have planned a ninety-guest wedding in Ravello in five months and a twenty-guest one at my own villa in three weeks. The difference is that you decide fast and you trust one person to hold the whole thing.